TL;DR
Wallonia has ordered Google to suspend construction of a three-hectare building at its planned Farciennes data centre, saying the structure lacked proper planning permission. Google says work is paused and has challenged a separate refusal to change the project’s cooling plans; a court hearing is scheduled for January.
Wallonia’s regional authorities have ordered Google to suspend construction of a building at its planned data centre in Farciennes, saying a three-hectare structure lacked proper planning permission. Google says it has paused the work and will comply with local law; the dispute also includes a rejected request to change the site’s cooling system to use water from the nearby River Sambre.
Regional inspectors visited the site on Thursday and told Google representatives to halt construction, according to the regional authority. Nicolas Yernaux, a spokesman for Wallonia, told AFP that officials had identified what he called “a major offense”: construction of a building covering three hectares without the required permission. The order was reported by AFP on November 27. The text of the order itself was not located in the source reporting.
The building sits within a former mining site of about 50 hectares, so the order concerns one structure, not the entire planned development. Google told the BBC it had paused the work “pending additional guidance” and said it remained committed to complying with local laws. The company has also challenged in court the regional refusal of its application to change the cooling plans. AFP reported that a hearing is scheduled for January.
The dispute over permission overlaps with concerns about water use. According to the reporting, the original project planned to use air cooling. Google later sought approval to use water drawn from the Sambre instead. Regional authorities rejected that application over the summer, amid concerns sharpened by severe drought conditions since spring, AFP reported. Reports available so far do not specify how much water the proposed system would use.
Stop-work order · court hearing pending
How a cooling plan became a stop-work order
At the heart of the row is water: how the computers are cooled, and where the water comes from.
- The planAir coolingThe original project planned to cool the computers with air, Belgian media reported.
- The changeRiver waterGoogle applied to cool the site with water from the nearby River Sambre.
- SummerRequest refusedAfter a dry spring, regional officials refused the change. Google went to court.
- This weekStop-work orderInspectors told Google to halt building. Officials call it a major offence.
- NextCourt in JanuaryGoogle says it paused the works and will follow local laws.
- Blue: the former mining site, some 50 hectares.
- Orange: the building of three hectares that officials say lacks proper permission.
Sources: AFP, as published by Arab News, November 27, 2026; BBC News, November 29, 2026. Schematic.
Graphic: Powered by Thorsten Meyer AI
Water and Permits Shape the Project
The order shows how planning approval and access to resources can affect the pace of data centre construction. Such facilities support cloud computing and AI services, but they require suitable land, power and cooling. A halt at a single building does not establish that the wider Farciennes project has been cancelled, but it may delay work while Google and regional authorities address the permit dispute.
For nearby residents, the central questions include how construction is authorised and what demands the facility could place on local resources. For Google’s cloud and AI customers, delays to planned infrastructure could affect when new capacity becomes available, though the reporting does not establish any impact on current services. The case also illustrates that local decisions can constrain large technology projects even when companies have broader investment plans.
Products Worth Considering

Samsung Odyssey G55C 32-Inch QHD 1000R Curved Gaming Monitor

Jackery Explorer 1000 v2 Portable Power Station

Sonos Roam Portable Bluetooth and Wi-Fi Speaker, Black
As an affiliate, we earn on qualifying purchases.
How the Cooling Dispute Developed
The planning dispute concerns both the building now subject to the halt order and Google’s requested change to the site’s cooling method. The regional government refused the water-cooling application over the summer. Greenpeace Belgium said in a report published this week that drone footage showed work continuing, and said the latest version of the planning permission had been revoked in August. Those are the group’s claims; the regional authority’s subsequent inspection and stop-work instruction were reported separately.
Greenpeace Belgium criticised the reported construction. Joeri Thijs of the group said, “That Google continues to build without a permit is disrespectful to the environment, local residents, and the law.” That statement reflects Greenpeace’s position, not a court finding. Google has not accepted that characterisation in the material provided; it says work is paused and that it is committed to following local laws.
Farciennes is not the only location where Google’s data centre construction has faced regulatory action. AFP reported that Finnish authorities halted work at two Google data centre sites in October. The cases are separate, and the available reporting does not establish that they share the same legal or environmental circumstances.
““We have operated in Belgium for over 15 years and remain committed to complying with local laws.””
— Google, in a statement reported by the BBC
Legal Status and Water Use Remain Open
The legal dispute has not been resolved. Google has challenged the refusal of its cooling-plan application, with a hearing scheduled for January, but the available reports do not give the court’s eventual decision or say whether the building can be legalised later. The order is in effect for now, and Google says construction is paused.
It is also not clear from the reported material whether Google’s challenge addresses the stop-work order itself, the refusal to alter the cooling plan, or both. The reports do not provide the full order, the complete permit record, or a detailed account of the regional authority’s legal reasoning. Nor do they state the volume of water Google proposed to draw from the Sambre or whether a revised air-cooling plan is under consideration.
Greenpeace’s account of continued construction is an allegation by an environmental group. Regional authorities have confirmed an inspection and ordered work to stop, but the available reporting does not include a court determination that Google violated the law. The scope and duration of the halt, beyond the building identified by officials, remain unclear.
January Hearing Will Test the Permit
The next reported milestone is the court hearing scheduled for January on Google’s challenge to the regional refusal of its cooling-plan application. The hearing may clarify the status of that decision, but the source material does not say whether it will also resolve the separate question of construction permission.
For now, Google says it has paused work while awaiting additional guidance, and Wallonia’s order applies to the building identified by regional officials. Further details from the court, the regional authority or Google could clarify whether the structure can proceed under revised plans, whether additional permission is required, and what cooling system the project could use.
Key Questions
Why did Wallonia order Google to stop construction?
Regional authorities said a three-hectare building at the Farciennes site was being constructed without proper planning permission. A regional spokesman called it a “major offense,” according to AFP.
Has Google stopped work at the site?
Google told the BBC it had paused the work “pending additional guidance.” The regional order concerns the building identified by officials; the reports do not say that the entire planned data centre site has been cancelled.
What is the dispute about the River Sambre?
Google sought to change the site’s cooling plan from air cooling to a system using water from the nearby River Sambre. Regional authorities refused the application over the summer, amid concerns about drought. The reported material does not state the proposed water volume.
When will the legal dispute be heard?
AFP reported that a court hearing on Google’s challenge to the refusal of its cooling-plan application is scheduled for January. The available reports do not specify the hearing date or whether it will also address the stop-work order.
Does the order affect the whole Farciennes project?
The reported order concerns one three-hectare building within a former mining site of about 50 hectares. The source material does not say that the whole project has been halted or cancelled.
Source: ThorstenMeyerAI.com